EconomicsRegulatory PolicyHardware & Semiconductors

FERC Preliminarily Declares Data-Center Grid Tariffs ‘Unjust and Unreasonable’

FERC's show-cause orders make the answer due August 17.

Josh LynwoodFounder
Published
Read time
10 min
Share
Where Things Stand

Nothing Changed Yet. The Burden Did, on All Six Operators at Once

On June 18, 2026 the Federal Energy Regulatory Commission, The Federal Energy Regulatory Commission, the federal agency that oversees wholesale electricity markets and interstate transmission., the agency that oversees wholesale power markets, issued show-cause orders to all six US regional grid operators at once, preliminarily finding their large-load interconnection tariffs unjust and unreasonable. The orders do not change any tariff yet; they flip the burden onto the operators to defend or fix their rules on a 60-day clock. Read together with the capacity prices already flowing into bills, the proceeding is less about connection speed than about cost allocation: who funds the grid the AI buildout needs. That through-line is an analytical judgment, not a claim the Commission has made.

  • The Orders. Six The Federal Power Act provision that lets FERC act on its own initiative when it finds an existing rate or rule unjust and unreasonable. show-cause orders, one per operator, in dockets EL26-67 (PJM), EL26-68 (SPP), EL26-69 (NYISO), EL26-70 (MISO), EL26-71 (CAISO) and EL26-72 (ISO-NE); together the six serve roughly 200 million Americans and about two-thirds of FERC-jurisdictional load across more than 30 states plus the District of Columbia.
  • Who Counts as Large. The orders define a large load as roughly 50 MW or more of peak demand interconnecting above 69 kV at a single site, and not co-located behind an existing generator.
  • What FERC Directed. Operators must address gross-versus-net demand-charge rules, cost-causation alignment, a minimum financial contribution from large loads with credit support (letters of credit, surety bonds or cash), Cost Recovery Agreements, contracts that pre-commit a large load to pay for the upgrades it causes, and public actual-versus-estimate load reporting.
  • The Clock. Interventions were due July 9, 2026; resource-adequacy reports are due July 20, 2026; the show-cause responses, where each operator proposes its answer, are due August 17, 2026.
  • The Trigger. Energy Secretary Chris Wright directed the review on October 23, 2025 under Section 403 of the DOE Organization Act, ordering a rulemaking on retail loads above 20 MW; FERC had never before exercised authority over retail-load interconnection, which is where the state-versus-federal seam opens.
Sources5See all 20
What did FERC actually order on June 18?

The Orders Rewrote No Tariff; the August Filings Will

Nothing final, and everything consequential. The orders preliminarily find that all six operators' tariffs fail to ensure large loads pay the costs they cause, and they direct each operator to show cause or propose reforms across a specific list: how demand charges are studied and billed on gross versus net load, how cost causation is applied, whether large loads must make a minimum financial contribution backed by credit support, whether Cost Recovery Agreements should pre-commit them to fund upgrades, and how actual load compares to the estimates used in planning. Because the finding is preliminary, no tariff has been struck down or rewritten. The responses due August 17, 2026 are where the actual rules get written.

The pressure behind the orders is already in the bills. PJM's capacity price, the amount paid to generators for being available, went from $28.92 per megawatt-day for 2024/25 to $269.92 for 2025/26 and then to $329.17, the FERC-approved cap, for 2026/27, a cumulative increase of roughly 1,038 percent across two consecutive auctions. December 2025's auction cleared at its $333.44 cap and, for the first time, short of the reliability requirement by about 6,625 megawatts.

PJM's independent market monitor attributes about $6.5 billion, roughly 40 percent, of the $16.4 billion 2027/28 capacity cost to data centers, including about $6.2 billion for centers not yet built. That is the arithmetic behind a 141-year-old Ohio brickmaker whose monthly capacity charge alone went from about $1,600 to about $12,000, and behind Maryland's roughly $1.6 billion cost-spreading complaint. Because Section 206 lets the Commission act on its own initiative, the burden now sits on the six operators rather than on complainants proving harm one docket at a time. The judgment here is that the proceeding is about cost allocation more than connection speed, and that through-line is a reading of the record rather than a claim the Commission has made.

Sources12See all 20
Intersections

A burden-flip puts who pays on a 60-day clock

Regulatory Policy. Because FERC acted under Section 206, the provision that lets the Commission move on its own initiative, the burden now sits on all six operators to justify or reform their large-load tariffs by August 17, 2026, rather than on complainants to prove harm one docket at a time.

Markets & Finance. Tariff language reprices risk across the capital stack: whether large loads pre-fund upgrades through Cost Recovery Agreements or inherit socialized charges changes the risk borne by utility equity, merchant generators and hyperscaler power contracts alike.

What would make this wrong

The operators' answers, whenever FERC's ruling requires them, propose no gross-basis billing, netting threshold or minimum contribution. The burden flip would have produced a defense of the status quo.

Open question

On the capital side: whether large loads pre-fund upgrades or inherit socialized charges is set in tariff language, so which of the six dockets writes the term the others copy?

Sources4See all 20
The Weave

The Weave maps a single development across domains and across time. Each row follows one domain from where things stand now through the next eighteen months, and expands for the reasoning behind that trajectory.

Wiiver
SECTOR / DOMAINclick a domain to expand
As It Standsthe current status
Immediate0–6 months
Near-Term6–18 months
Business + Markets
The cost shift is in industrial bills now. An Ohio brickmaker's monthly capacity charge rose from about $1,600 to $12,000.
Capacity costs are already socialized
Belden Brick's capacity charge alone went from about $1,600 to about $12,000 a month, while its total power cost rose roughly 90 percent, per Reuters.
Cost-causation reassignment has a template
Oregon's Schedule 96 raised data-center rates about 29 percent and cut residential rates about 1.3 percent; Virginia's SCC class starts January 2027.
PJM's capacity price is pinned at its cap, and the December 2025 auction cleared short of the reliability requirement.
Tariff language reprices risk
Whether large loads pre-fund upgrades or inherit socialized charges sets the risk in utility equity, merchant generation and hyperscaler contracts.
The fight moves from price to allocation
PJM's December 2025 auction cleared at its $333.44 cap and, for the first time, short of the reliability requirement; price no longer resolves scarcity.
Government + Policy
Six Section 206 show-cause orders are open and nothing is final. Every grid operator must answer by August 17, 2026.
The burden flips to the grid operators
FERC's Section 206 orders preliminarily find all six operators' large-load tariffs unjust and unreasonable and put each on a 60-day clock.
Net-versus-gross decides who pays
The August 17, 2026 filings must answer whether grid operators bill large loads on net draw or full gross peak.
Technology + Engineering
AI racks concentrate demand well above legacy density. A GB200 NVL72 rack draws about 120 kW against 5 to 15 kW.
AI racks are the load shock
A single GB200 NVL72 rack draws about 120 kW against 5 to 15 kW for legacy racks, an intensity the interconnection rules were never written for.
HBM supply is the near-term throttle
The binding constraint is upstream: high-bandwidth memory and accelerator availability, not grid permits or siting announcements.
wiiver.co · 4 impacted domains shownWiiverv1 · July 8, 2026
Looking Forward

The Responses Decide Allocation. The Price Cap Cannot

Whether this proceeding reallocates costs or ratifies the status quo will show up in a handful of checkable signals between now and the fall.

  • July 20, 2026. The resource-adequacy reports each operator must file, the first system-wide, on-the-record account of how much of the demand surge is real, committed load versus speculative queue entries.
  • August 17, 2026. The show-cause responses: whether each operator proposes gross-basis billing, where it sets the maximum netting threshold in MW, and what minimum financial contribution and Cost Recovery Agreement terms it attaches.
  • Manufacturer Carve-Outs. Whether the responses distinguish a 60 MW factory from a 3,000 MW campus, the factor-of-50 mismatch the Reuters investigation surfaced, or leave mid-size industrial loads inside hyperscaler-shaped rules.
  • The Maryland Complaint. How FERC disposes of the Office of People's Counsel's ~$1.6 billion cost-spreading complaint, and whether other PJM states file parallel challenges.
  • The Next Capacity Auction. Whether PJM prices stay pinned at the cap and whether the market again clears short of its reliability requirement, the condition that moved the fight from price to allocation.
Sources7See all 20

Every issue

  1. 01Intersection of the week
  2. 02Impact of the week
  3. 03The week in review

Wiiver Weekly

One free email, Saturdays at 7:00 AM ET.

Unsubscribe anytime.

Sources and Verification
9 of the 20 sources cited here are primaryfilings, opinions, statutes and agency releases read directly
Primary sources9
Secondary sources, by sector11
Government + Policy1
Business + Markets9
v2 · Reviewed by Josh Lynwood · July 8, 2026
Back to top